Project Schedule

Phase/MilestoneMonthTasksDeliverables
1
Preparation
Aug 2024– Brainstorm ideas and confirm topic (10)
– Perform background research on algorithmic trading (20)
– Conduct market research on investment apps (15)
2
Planning
Sep 2024– Consult project supervisor (5)
– Define project scope (5)
– Define project objectives (5)
– Define main features (5)
– Research on various algorithmic trading strategies (20)
– Prepare the detailed project plan (15)
– Prepare the project web page (5)
2 Oct 2024
– Detailed project plan
– Project web page
3
Implementation
Oct 2024– Research and implement various algorithmic trading strategies (40)
– Perform back testing in different markets and various market conditions (20)
Nov 2024– Propose enhancements on existing algorithmic trading strategies (30)
– Explore the feasibility of incorporating different textual data (30)
4
Prototyping
Dec 2024– Explore the feasibility of related articles collection and summarisation (10)
– Design and implement the dashboard to summarize key insights (20)
– Design and implement the integrated investment app (20)
5
Testing
Jan 2025– Minimal Viable Product (MVP) prototype ready (10)
– Prepare the interim report (20)
27 Jan 2024

Preliminary implementation and prototype

Prototype testing

Interim Report
6
Fine-tuning
Feb 2025– Implement remaining functionalities (30)
– Improve the product according to feedback from stakeholders (30)
Mar 2025– Implement the final algorithmic trading strategy (20)
– Cut off back testing and organise the results (20)
Apr 2025– Prepare the final report (20)
– Prepare for the final presentation (10)
– Prepare the poster (5)
22 Apr 2025
– Implementation of the final product
– Final Report

Note: Estimated learning hours for each milestone are indicated inside the parenthesis